Set-up a Part with Subcontractor Costs for Installation

In this example, we'll take a look at how you can create a part that includes Material Cost for materials, but uses a Subcontractor for the installation cost.

Simple Steps

  1. Open the part with the blue "edit" button
  2. Un-check the "Labor Cost Calculation" box to remove the Labor Cost
  3. Check the "Subcontractor Cost Calculation" box to include Subcontractor Cost for installation
  4. Change "Subcontractor Cost Calculation" to "$/unit"
  5. Enter the dollar amount per unit for installation

Example

For this example, we'll assume $10.00/sq ft for Material Cost, and $5.00/sq ft for Subcontractor Installation: